30 KLPD Retort Drinks Factory: Expansion Project

THE BRIEF

End-to-End Engineering Assessment, Engineering Design, Procurement and Contracting, Project Management and Construction Supervision

HIGHLIGHT
30 KLPD Retort Drinks : Expansion processing capacity
HIGHLIGHT
Brownfield expansion of existing facility
KEY CHALLENGES
Tie-in with running production with minimal downtime
Brownfield space
utility and access constraints
Phased commissioning around live operations
FAQ
What did PMG deliver on this project?
PMG provided Engineering Design for an expansion 30 KLPD Retort Drinks Factory: Expansion Project at Parag Milk Foods Ltd's facility in Palamaner, Andhra Pradesh, India.
When was this project executed?
PMG executed this project between November 2018 and December 2018, spanning approximately 2 months from kick-off to handover.
What is the capacity scope of this project?
The scope covers 30 KLPD Retort Drinks : Expansion.
What industry does this facility serve?
This is a Food and Beverage facility in the Dairy Products segment. PMG's design and execution follow F&B sector hygienic engineering and food-safety practices.