Munch Chocolate Factory: Commissioning Supervision
THE BRIEF
100 TPD Delicacy factory for Nestlé. Designed, procured & construction-supervised by PMG Engineering.
HIGHLIGHT
Brownfield expansion of existing facility
HIGHLIGHT
Multi-service PMG engagement
KEY CHALLENGES
Tie-in with running production with minimal downtime
Brownfield space
utility and access constraints
Phased commissioning around live operations
FAQ
What did PMG deliver on this project?
PMG provided Project Management and Construction Supervision for an expansion Munch Chocolate Factory: Commissioning Supervision at Nestlé's facility in Tahliwal, Himachal Pradesh, India.
When was this project executed?
PMG executed this project between September 2021 and February 2022, spanning approximately 5 months from kick-off to handover.
What is the production capacity of this facility?
The facility is designed for approximately 100 TPD of throughput.
What industry does this facility serve?
This is a Food and Beverage facility in the Delicacy segment. PMG's design and execution follow F&B sector hygienic engineering and food-safety practices.