Change Requests — Risk & Change — Workspace
Manage scope changes with cost and schedule impact tracking
Overview
Change Requests manage formal scope changes through a structured workflow
from draft to implementation. Each request captures the reason for the
change, its estimated cost and schedule impact, and follows a
decision-making process with full audit trail. Approved changes can be
linked to implementation tasks for execution tracking.
Change Request list with status badges and priority indicators
Raising a Change Request
Click Add on the Change Requests page:
Requested By — a member of the team, or the client who asked for the change. Search by name or organisation; someone new can be added right there with Add “…” as an external person, and is then in Organization → External for everyone.
Title — what is being changed.
Description — detailed explanation of the proposed change.
Reason — why the change is needed.
Priority — Low, Medium, High, or Critical.
Cost Impact (optional) — estimated cost of the change in your project currency.
Schedule Impact (optional) — estimated impact in days.
Deliverables — which scope items are affected.
Milestones affected — the milestones this change will move. When the request is approved they move by the s…